1. One week prior to the start of Iteration 5, which is planned for a two weeks duration, the BPM Program Manager has asked developers to review the proposed user stories assigned to the iteration, define implementation tasks and provide estimates in hours. During the commitment meeting prior to iteration start, one of the user stories has a single implementation task with an estimate of 80 hours. What should the BPM Program Manager recommend?
A) Break down the user story into child stories because it is an epic.
B) Break down the implementation work into tasks that can be described in 8 hours or less.
C) Cancel the user story and move it to a future iteration because 80 hours too large to fit into a two-week iteration with confidence.
D) Pad the task with 20% more hours because developers typically under-estimate their required effort.
2. A company needs to speed up its hiring process. A proposal to accomplish this goal is modeled in the following BPD diagram and run against historical data with the Optimizer. The proposed process no longer waits for the background check to complete before putting the new hire into orientation and training.
What is the Service Level Agreement (SLA) that is key to optimizing this process?
A) Total time on "Facilitate New Hire's Orientation".
B) Wait time on "Background Check".
C) Percentage of new hires that fail "Background Check".
D) Percentage of new hires that pass "Probationary Review".
3. When documenting an activity in a business process, the BPM Analyst will record the business objects used by that activity. How will the BPM Analyst document the business objects used (or created) by that activity?
A) process activity inputs and outputs
B) process activity steps
C) process variable types
D) process participant requirements
4. In the Playback 0 review session, the executive sponsor for BPM suggested adding a requirement to the business process not previously articulated. The executive sponsor would like to see the business requirement implemented by the next playback validation session. How should the program manager handle the previously unknown business requirement?
A) Find the best time in the development effort when resources are available to insert the business requirement implementation.
B) Proceed with Playback 1 and include the new requirement in the set of requirements for the development phase.
C) Validate user story with process owner and schedule for a later iteration.
D) Explain to the executive sponsor that the requirement will be implemented in the next iteration.