최신 IBM Certified BPM Program Manager A2180-188 무료샘플문제:
1. The BPM program manager and process owner for a new hire onboarding process project need to ensure that the solution developed by the team will be accepted and adopted by the target users. To facilitate this, they decide to:
A) insist on documentation of all user requirements before having the development team begin work.
B) agree with users to postpone the release until every feature is correct.
C) involve champion SMEs in the discovery and implementation including playbacks.
D) plan additional playbacks for user screens.
2. The purpose of a snapshot is to:
A) provide security against unauthorized access and alteration of process applications.
B) record the state of a process application or toolkit at a specific point and time.
C) allow developers and business users to collaborate on business process definitions.
D) use it to record revision history of library items.
3. A process owner needs to monitor the performance of multiple processes in the aggregate. What should the program manager plan on developing first to satisfy this requirement?
A) A report
B) Key Performance Indicators (KPIs)
C) Service Level Agreements (SLAs)
D) Scoreboards
4. The BPM analyst, Process Owner and BPM program manager have created a list of user stories with point estimates. What do user story points measure?
A) The value of the user story.
B) An approximate, relative measurement of the development effort.
C) The time in hours required to implement the user stories.
D) The priority of the user story.
질문과 대답:
질문 # 1 정답: C | 질문 # 2 정답: B | 질문 # 3 정답: B | 질문 # 4 정답: B |