1. Which one of the following is a specific objective of a quality review?
A) Baseline the product for change control purposes
B) Perform an assessment on the performance of the Presenter of the product
C) Update the Stage Plan with the details of the quality review progress
D) Produce a Product Status Account for the products under review
2. Identify the missing word(s) in the following sentence... The development and maintenance of a credible [?] provides a baseline against which progress can be measured.
A) Product Status Account
B) Business Case
C) Plan
D) Product
3. What is the first task of the product-based planning technique?
A) Create a product breakdown structure
B) Write the Project Product Description
C) Write Product Descriptions
D) Identify activities and dependencies
4. Which process would ensure that there is continued business justification?
A) Initiating a Project
B) Directing a Project
C) Managing a Stage Boundary
D) Starting Up a Project
5. Which of the following would be carried out as part of a post-project benefits review?
A) A review of the performance of the project management method and the project management team
B) An assessment of whether the project fulfilled its original objectives
C) An assessment of the project's risk management procedure
D) A review of the performance of the project's products in operational use and identification of whether there have been any side-effects
질문과 대답:
질문 # 1 정답: A | 질문 # 2 정답: C | 질문 # 3 정답: B | 질문 # 4 정답: B | 질문 # 5 정답: D |