최신 BCS Certification PRF 무료샘플문제:
1. Which describes a risk effect?
A) The uncertainty expressed as a negative or favourable occurrence
B) The impact(s) on the project objectives should the threat or opportunity occur
C) The change in the status of a risk in response to actions taken to control it
D) The issue which is affecting the project and has resulted in a risk
2. Which enables the project's products and all interdependencies to be clearly identified and documented?
A) Product-based planning technique
B) Quality Management Strategy
C) Product breakdown structure
D) Quality review technique
3. Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A) Product Status Account
B) End Stage Report
C) End Project Report
D) Checkpoint Report
4. Identify the missing words in the following sentence.
The Team Manager should check the [ ? ] for any interfaces that must be maintained while developing products.
A) Work Package
B) Project Plan
C) Checkpoint Report
D) Project Product Description
5. Which is a type of issue?
A) A project outcome
B) An expected dis-benefit
C) An off-specification
D) A scope tolerance
질문과 대답:
질문 # 1 정답: B | 질문 # 2 정답: A | 질문 # 3 정답: B | 질문 # 4 정답: A | 질문 # 5 정답: C |