최신 CompTIA Project+ PK0-400 무료샘플문제:
1. A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
A) Cost plan
B) Scope statement
C) Impact assessment
D) Project schedule
2. During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A) 16 days
B) 12 days
C) 19 days
D) 14 days
3. There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A) A, B, F
B) D, E, H
C) D, B, F
D) A, C, G
4. Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
A) Marketing representative
B) Product item
C) Sales clerk
D) Team lead
5. A project team is comprised of a mix of in-house and virtual team members.
When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?
A) Sending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.
B) Composing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.
C) Using text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.
D) Hosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.
질문과 대답:
질문 # 1 정답: D | 질문 # 2 정답: B | 질문 # 3 정답: B | 질문 # 4 정답: A | 질문 # 5 정답: D |