1. A project plan is a:
A) document describing the organizational breakdown structure of the company.
B) formal, approved document used to guide both project execution and project control.
C) narrative description of products or services to be supplied.
D) document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.
2. In which project management process is the detailed project budget created?
A) Executing.
B) Initiating.
C) Planning.
D) Closure.
3. To which of the following tools is SAP P20 linked?
A) RTI.
B) NRisk.
C) IPM.
D) NELLE.
4. Which of the following documents are NOT part of the PTA handover from Sales to Delivery?
A) WBS structure.
B) Logistics plan.
C) Project management/delivery plan.
D) Cost baseline.
5. Which milestone(s) must always be completed before invoicing?
A) It depends on the contractual terms.
B) Provisional acceptance.
C) Final acceptance.
D) Internal acceptance.
질문과 대답:
질문 # 1 정답: B | 질문 # 2 정답: C | 질문 # 3 정답: C | 질문 # 4 정답: A | 질문 # 5 정답: A |