1. Identify the missing words in the following sentence. An objective of the Directing a Project process is to [?] throughout a project's life,
A) define the benefits to be realized
B) document how risks will be managed
C) identify who will be responsible for quality
D) provide management direction and control
2. Which is a purpose of a Project Product Description?
A) Document the project mandate and gain approval for the project from the Project Board
B) Form part of the Work Package for the project product
C) Provide the initial project budget to be refined in the Business Case
D) Define the quality required of the project's product
3. Which is NOT a requirement of a Stage Plan?
A) Approved at the end of a management stage
B) Produced near to the end of the previous management stage
C) Approved and signed-off by Project Assurance
D) Produced to an appropriate level of detail to enable day-to-day control
4. Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
A) Neither 1 or 2 are true
B) Both 1 and 2 are true
C) Only 1 is true
D) Only 2 is true
5. Which is a purpose of a Project Brief?
A) Capture lessons from previous projects
B) Confirm that the Project Plan is able to deliver the Business Case
C) Ensure that there is a common understanding of the starting point for the project
D) Define the quality techniques and standards to be applied during the project