최신 SAP Certified Application Associate C_IBP_2105 무료샘플문제:
1. Which of the following solutions are feasible when using the time series supply optimizer? Note: There are 3 correct Answers to this question.
A) Not adhering to maximum transport values
B) Not respecting production capacity
C) Not-fully satisfied demands
D) Violation of minimum aggregated inventory values
E) Violation of minimum resource utilization
2. You need to define a new logic for a key figure to drive values from the PERPRODCUSTREGION level to the PERPRODCUST level. Which of the following configuration options are possible for this process?
Note: There are 2 correct Answers to this question.
A) Splitting the values from aggregated to detailed level using multiplication by the proportions
B) Splitting the values from detailed to aggregated level by using copy operator
C) Splitting the values from aggregated to detailed level based on time profile attribute
D) Splitting the values from aggregated to detailed level based on stored split-factor key figure
3. Which of the following checks for master data and key figures does the Check Mode algorithm trigger?
Note: There are 3 correct Answers to this question.
A) It checks whether the heuristic detects cycles formed by nodes (such as location products) in the supply chain network.
B) It checks whether the location products specified in the master data are connected by customer sourcing rules within the supply chain network.
C) It checks whether the sourcing in the Production Source Item Master Data type exists.
D) It checks whether the required planning level master data exists for a subset of input key figures.
E) It checks whether the location resource specified in the master data forms a cycle in the supply chain network.
4. Model configuration allows the attributes of a master data type to be assigned as key figures. Which features are relevant for this type of object?
A) This object provides a single value for a unique planning combination.
B) This object contains user-defined criteria that monitor execution of business plans.
C) This object is not exposed to the user in planning views or modeling.
D) This type of key figure is not usually stored and it cannot be set to editable.
5. You create an S&OP operator for heuristics on an SAP IBP project. What must you enable for the S&OP operator that is specifically relevant for subnetworks?
A) Compute Expected Supply parameter
B) Normalize Quotas parameter
C) Supply propagation
D) Balance Receipts parameter
질문과 대답:
질문 # 1 정답: C,D,E | 질문 # 2 정답: A,D | 질문 # 3 정답: A,B,D | 질문 # 4 정답: A | 질문 # 5 정답: A |