최신 SAP Application Associate C-TSCM42-64 무료샘플문제:
1. Which of the following structural elements does a process order have? (Choose three.)
A) Phases
B) Parallel sequences
C) Characteristic-based process instructions
D) Item data
E) Relationships
2. Which of the following situations occur when a production order is set to Technically Complete (TECO)? (Choose three.)
A) Purchase orders for external operations or non-stock materials are deleted.
B) The order is no longer relevant for Material Requirements Planning.
C) Reservations are deleted.
D) Capacity requirements are deleted.
E) The order and its operations receive the system status Locked (LKD).
3. Which production order function can no longer be carried out after the order is released?
A) Posting a goods receipt from production to stock.
B) Read PP master data.
C) Switching sequences.
D) Posting a goods issue from stock to the production order.
4. In SAP ECC, a customer tests the firming options for planned orders. The customer first sets the manual firming date from the stock/requirements list to firm planned orders that shall occur in the short term. In the material master, a rolling planning time horizon with firming type 1 is active. Some planned orders have also been firmed manually already.
Which statement applies for the resultant firming situation?
A) The firming interval is specified by the planning time fence from the material master, because this always overrides the manual firming date; all the manually firmed planned orders are firmed independently of this.
B) The firming interval is specified by the firming mechanism that currently stretches further into the future; all the planned orders within this horizon are firmed only if they were previously firmed manually.
C) The firming interval is specified by the manual firming date because it always overrides the planning time fence from the material master; all the manually firmed planned orders are firmed independently of this.
D) The firming interval is specified by the firming mechanism that currently stretches further into the future and which firms planned orders that are within it; all the manually firmed planned orders are firmed independently of this.
5. With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)
A) Material identification and reconciliation
B) Resource selection
C) Digital signature
D) Batch record
E) Availability check
질문과 대답:
질문 # 1 정답: A,C,E | 질문 # 2 정답: B,C,D | 질문 # 3 정답: C | 질문 # 4 정답: D | 질문 # 5 정답: A,C,D |