1. You have set up infinite S&OP Heuristics for unconstrained planning. What must you do to model inputs as constraints?
There are 2 correct answers to this question.
Response:
A) Enter transportation lead times.
B) Set minimum and maximum lot sizes.
C) Create product substitutions.
D) Model adjusted transport receipts.
2. You created a time profile and want to use time levels. In which of the following cases is it mandatory to set the time level?
There are 2 correct answers to this question.
Response:
A) Choose a time profile level in a planning view in Microsoft Excel.
B) Maintain a time profile level as parameter in a disaggregation planning operator.
C) Assign a time profile level during the load of key figure values with the Data Integration Jobs app.
D) Assign a time profile level for a planning level of a planning area.
3. Which input parameters can you use to limit the scope of your supply planning run?
There are 3 correct answers to this question.
Response:
A) Versions
B) Permission filter
C) Time periods
D) Product locations
E) Subnetwork
4. You need to monitor the capacity of your Distribution Center goods receipt employees. Every goods receipt takes two working days of a warehouse employee.
How would you model this?
Please choose the correct answer.
Response:
A) Maintain a storage resource on the DC and maintain the number of days on the location product attribute.
B) Maintain a regular production resource and change the description in goods receipt employee capacity. Maintain the number of days on the location product attribute.
C) Maintain a handling resource with available capacity on the DC and maintain the number of days on the location product attributes.
D) Maintain a warehouse-resource on the DC and maintain the number of days on the location product
5. Which of the following functional areas are included in the out-of-the-box Integrated Business Planning Sales and Operations model provided by SAP?
There are 3 correct answers to this question.
Response:
A) Executive review
B) Consensus demand planning
C) Finite resource capacities planning
D) Demand Driven Materials Requirement planning
E) Rough cut supply planning