최신 Business Process Management 1z0-1125-2 무료샘플문제:
1. After OEM completes tracking a work order and the supply is available, who sends the shipping req and to whom?
A) Production Supervisor to OEM
B) CM to OEM
C) OEM to CM
D) Production Supervisor to CM
2. Which task is used to upload an external forecast in the system?
A) Refresh and start the Order Promising Server
B) Load planning data from files
C) Export supply chain planning data
D) Load filter names for planning data collections
3. What are the planning levels available for Min-Max planning?
A) Organization, Sub inventory, Locator, Project, and Item
B) Organization, Sub inventory, Locator, and Item
C) Organization, Sub inventory, and Locator
D) Organization and Sub inventory
4. Which work order costs CANNOT be viewed and analysed by a cost accountant on the Review Work Order Cost page?
A) Shipping Costs
B) Output Costs
C) Scrap Costs
D) Transfer Cost
5. What is the purpose of defining the ABC Classification?
A) To decide the frequency to review inventory balances
B) To decide the frequency to perform inventory transactions
C) To decide the frequency to perform inventory replenishment
D) To decide the frequency to perform inventory accuracy review
질문과 대답:
질문 # 1 정답: C | 질문 # 2 정답: B | 질문 # 3 정답: D | 질문 # 4 정답: A | 질문 # 5 정답: D |