최신 Project Financials Management Cloud 1Z0-1057-21 무료샘플문제:
1. You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
A) The association of a deliverable with a task is dependent on associating a requirement with a task.
B) A deliverable associated with a requirement is automatically associated with the tasks createdfor that requirement.
C) Youassociate a deliverable with a task, independent of associating a requirement with a task.
D) A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
2. Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these classcategories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
A) Class codes should be assigned to project unit.
B) Class categories should be assigned to business unit.
C) Class codesshould beassociated
D) Class categoriesshould beassignedtoproject type.
3. Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accountingclose cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)
A) Daily Spread Basis
B) Back Loaded
C) S-Curve
D) Bell Curve
E) Even
4. As part of maintaining (importing new employees thatwere added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Whichthreeare parameters that are based on which the system identifies the new resources?
A) Jobs
B) Department
C) Organization
D) Business Unit
E) Project Unit
5. Whichfivesteps are required for the File-Based Data Import Integration option?
A) Install an Excel add-in.
B) Download an Excel template.
C) Import data into various applications.
D) Upload the file to the server.
E) Run Process to transfer data to interface tables.
F) Populate the spreadsheet with data and generate a CSV file.
질문과 대답:
질문 # 1 정답: C,D | 질문 # 2 정답: C,D | 질문 # 3 정답: A | 질문 # 4 정답: A,C,D | 질문 # 5 정답: A,B,D,E,F |